Showing posts with label 司法审核. Show all posts
Showing posts with label 司法审核. Show all posts

Friday, 16 November 2012

LYNAS – THE JOURNEY TO NOWHERE

WHY the CEO sold so much of his own shares in LYC last year if its such a lucrative company ?


Here is of a piece of comment shared by rare earth market analyst:  
 

LYNAS – THE JOURNEY TO NOWHERE


Back in January this year, investors were becoming dispirited with progress on LAMP completion.  I wrote an article for this site called “Where Lynas is at”.  My final summation was:
“Clearly, Lynas will no longer be the same company after POL approval.  It should be one heavily in demand.  At a time when investors are looking for a safe place to invest, yet one with outstanding returns, many will want to be a part of it.”
The article was premature and I strongly regret writing it.  10 months later, the LAMP has been completed  less than 2 months, the Pre-Operating Licence has been approved, issued and then suspended.  It remains suspended.
Along the way, I have seen countless strong supporters of the company lose most of their assets as the continued delays and uncertainties have allowed the big players to control the market and manipulate the share price as low as 56 cents.
The uncertainties have been greatly assisted by the poor flow of, at times misleading, information from the company.  I will detail what the company has done, how it has poorly informed the market over a considerable period.  It has been the light on the hill on a dark night, enticing us to stagger to the top only to see that light extinguished and another one to appear on the next hill.  And so on.
The LAMP was originally scheduled to be in production by 30/06/11.  Not only is it still not producing, there is not one iota of confidence that it will ever produce.
In my view, the situation has now become so bad that a Trading Halt should be imposed until the market is once again fully informed that the LAMP can either operate or it can’t.
Just follow this timeline of company announcements and see if you agree with me about how the market has been misled:
Sojitz Funding announcement 30/3/11
Budgeted Phase 1 construction costs are fully funded
•The Mount Weld Concentration Plant is completed and is ready for the first feed of ore. Lynas is working on satisfying the final requirements of the WA Department of Environment, which are taking longer than expected to satisfy. Lynas expects to satisfy those requirements within 3 to 4 weeks, and Lynas understands that start up of the Mount Weld Concentration Plant will occur upon satisfaction of those requirements
•The Lynas Advanced Materials Plant (LAMP) is due to be commissioned in 3Q 2011
•All approvals in Australia and Malaysia are in place to complete construction of processing plants
•All major equipment procured
•Lynas has signed six supply contracts and two letters of intent in relation to future production
(The market has now been informed that 30th June completion will not be achieved.  Completion is now going to happen some time during the next 3 months.  Deliberately not very precise?  This advice is from experts in construction of such plants who not so long before were assuring us that completion would be by 30/6! A later announcement was more precise and used a September date for completion.  Couldn’t be October because that was in the 4th quarter, wasn’t it, and the Company didn’t want to let on just yet that the 3rd quarter wasn’t going to be achieved.)
5 Million Hours LTI Free Achieved at Lynas Advanced Materials Plant 30 September 2011
Lynas Corporation Limited (“Lynas”) (ASX:LYC, OTC:LYSDY) is pleased to announce a major milestone in achieving 5 million hours Lost Time Injury (“LTI”) free in the development and continuing construction of the Lynas Advanced Materials Plant (LAMP) in the Gebeng Industrial Estate, near Kuantan, Malaysia.
The Concentration Plant in Western Australia commenced feed of ore on 14 May 2011 and is performing well. First feed of concentrate at the LAMP is scheduled to be achieved in the fourth quarter of 2011. Lynas has received all required approvals to construct the LAMP, and is in the process of applying for all pre-operation and operation approvals.
(Ah, the 30th of September has now come, so the Company has to announce a later completion date.  Again, it is unhelpful to the market by advising an imprecise time of “fourth quarter of 2011”.  Some investors were able to imagine a possible date of 31/10, some, no doubt were more careful and thought 30/11 more likely, and the rest had every right to believe 31/12/11 was as late as it could go.  Weren’t we all sadly mistaken?!
Quarterly Report 31/10/11
Slight delays in final procurement packages and associated delays in construction and contractor resourcing means it is likely that  first feed to kiln will not occur until early Q1 2012.
For once the company didn’t wait till 31/12 to announce they were wrong – they strung us out that little bit further with “early Q1 2012”.  Now, you could think that might be early January or even early February but certainly not early March.  In any case, whatever you thought that announcement meant, you would have been wrong.
The Chairman, Nick Curtis, gave his address at the AGM on 30/11/11 and said:
 “This time next year I will not be reporting to you the sales we are about to achieve, but rather celebrating with you the reality of our production and sales, and speaking again of the huge potential of our business.”
He also said the LAMP was 78% complete as at 30/9/12.  He didn’t say that with 22% still to go, there was no chance of the deadline of early first quarter 2012 being met.  That was his opportunity to confess to the delays but he said nothing.  Nothing other than that ridiculous statement above which is also clearly false.
Early first quarter 2012 was almost past before he announced as part of the Mt Kellet funding announcement:
“Additional engineering completion requirements and consequential delays in procurement, as well as the recent monsoon season, are the primary causes of the delay for LAMP Phase 1. Based on the latest information from the construction manager, Lynas anticipates first feed to kiln and first production during the second quarter of 2012, subject to regulatory compliance and issuance of the pre-operating licence for the LAMP.”
2 months had gone by during which it must have been clear to all in the Company that the previous deadline of early quarter 1 2012 would not be met.  Why did he wait so long before informing the market?
Another month passed before the next announcement.  It was the Investor Presentation 14/02/12
“LAMP construction: 91% complete
Ready-for-Start-Up program (operational preparedness): 91% complete
Malaysia headcount: 236 (now at 85% of total expected workforce)
Pre-commissioning test packs: 33% complete
Temporary Operating Licence for the LAMP approved
Lynas is on track for first feed to kiln and first production in Q2 2012.
This was fantastic news.  All the market could think of was that TOL had been approved.  In the euphoria and with the lack of Company explanation, the market believed “TOL approved” meant production could start as soon as the LAMP was ready.  Not so, not so.
30/04/12
“On 1 February, Malaysia’s Atomic Energy Licensing Board (AELB) announced its approval of the Temporary Operating Licence (TOL) for the LAMP in Gebeng, Malaysia. The AELB’s approval decision came after a thorough and extensive review of the project by the Malaysian Government regulatory authorities. An appeal in respect of the AELB’s decision has been lodged with the Minister of Science, Technology and Innovation. The Minister’s decision is expected shortly.
As at the end of the period, construction of Phase 1 of the LAMP was 98% complete and pre-commissioning test-packs were more than 85% complete. Lynas is on track for first feed to kiln in Q2, subject to the issuance of the TOL. “
3 months after approval, we were informed that TOL still had to be ISSUED.  “Approved” didn’t mean approved at all.  Production couldn’t start till TOL was ISSUED.  Oh, shit.  In the midst of that disappointment, the Company lifted our spirits by claiming it was on track “for first feed to kiln in Q2”.  Clearly, the LAMP at “98% complete” was going to ready to go by 30th June.
“PARLIAMENTARY SELECT COMMITTEE IN MALAYSIA UPDATE 20 June 2012
Lynas Corporation (ASX:LYC, OTC:LYSDY) advises that the report of the Parliamentary Select Committee (PSC) established in relation to the Lynas Advanced Materials Plant (LAMP) was debated in the Malaysian Parliament on 19 June 2012.
As previously announced on 19 March 2012, the Malaysian Government established the PSC with the purpose of helping to raise public awareness concerning the LAMP.
In tabling its report, the PSC makes clear that it has taken into consideration a broad range of issues raised by concerned citizens, special interest groups and NGOs relating to public health and environmental safety, and subjected the LAMP to intense independent, expert scrutiny.
The report recommends that the Temporary Operating Licence (TOL) be issued for the LAMP. In addition, the report notes that Lynas has complied with the standards and laws in Malaysia, which are in line with international standards.”
This again showed that the government believed the TOL should be ISSUED.  Why then, did the AELB not issue it right there and then?  Of equal importance, why did Lynas not use the opportunity to tell the market its 30th June deadline for completion in only 10 days time was not going to be met?!
Quarterly Activities Report 31/7/12
“The Lynas Advanced Materials Plant (LAMP) Phase 1 construction project in Malaysia was completed Lost Time Injury (LTI) free. The project involved a total of 8,690,000 hours worked without an LTI. Subsequent to the end of the reporting period Lynas Malaysia remains LTI free.
• On 18 June 2012, Lynas announced that the Ministry of Science, Technology and Innovation (MOSTI) Minister, Datuk Seri Panglima Dr. Maximus Johnity Ongkili dismissed the appeal that was lodged under Section 32 of the Atomic Energy Licensing Act in relation to the decision of the Malaysian Atomic Energy Licensing Board (AELB) to approve the issuance of a Temporary Operating Licence (TOL) for the LAMP.
• Lynas also welcomes the findings of the Malaysian Parliamentary Select Committee (PSC) report on the LAMP which recommended that the TOL be issued for the LAMP. The report noted that Lynas has complied with the standards and laws of Malaysia, which are in line with international standards.
• Construction of Phase 1 of the LAMP was completed during the quarter and further progress was made on various pre-commissioning activities. Overall commissioning progress was 64% complete as at the end of the quarter. Construction of the Phase 2 expansion of the LAMP continued during the period and is on track for construction completion in early 2013.”
It waited a full month past the deadline before informing the market that in fact, the LAMP had been completed during June.  Right…so what was this next announcement about?
 “LYNAS Phase One LAMP complete 28 August 2012
Lynas Corporation Limited (Lynas) (ASX:LYC, OTC:LYSDY) has completed Phase One construction of the Lynas Advanced Materials Plant in Malaysia.”
Clearly REAL completion did not occur till 28/8.  Or is it still not complete?  Who knows?  Not I.
“LYNAS RECEIVES TEMPORARY OPERATING LICENCE 5 September 2012
Lynas Corporation Limited (“Lynas”) (ASX:LYC, OTC:LYSDY) confirms that the Malaysian Atomic Energy Licensing Board (AELB) has today issued the Temporary Operating Licence (TOL) for the Lynas Advanced Materials Plant (LAMP).”
So on 5/9/12, the TOL (already approved in February!) was finally issued.  The LAMP was ready to go, concentrate could be imported and production could start.  No, no, not quite.  Somehow, the TOL issue was able to be suspended.  So it is now an approved, issued but suspended licence.  I could ask in wonder, “Who is in charge of Malaysia?”  We all must wonder.
Meanwhile, Lynas has suddenly started informing the market of important developments.  Oh well, it did wait 5 hours before passing on the information about TOL issue being suspended but that didn’t surprise me one bit.  If these court decisions aren’t price sensitive then I know nothing.  Lynas should be in a Trading Halt while these cases run.  I don’t just mean the day of the court appearance, I mean until a decision is handed down.  A FINAL decision.  That is the only way to stop the manipulation of the share price by people who already know the outcome of the legal proceedings.
“UPDATE ON MALAYSIAN LEGAL PROCEEDINGS  25 September 2012
Further to Lynas Corporation Limited’s (ASX:LYC, OTC:LYSDY) announcement dated 10 September 2012, the Kuantan High Court has decided to hear on 4 October 2012 an application by parties associated with the Save Malaysia Stop Lynas group for an injunction in respect of Lynas’ Temporary Operating Licence (TOL). The injunction application is part of an application seeking judicial review in respect of the June 2012 decision of the Minister of Innovation, Science and Technology to affirm the approval of the TOL.”
MALAYSIAN COURT UPDATE  4 October 2012
Lynas Corporation (ASX:LYC, OTC:LYSDY) provides the following update to its ASX announcement dated September 25, 2012, relating to a judicial review of the company’s Temporary Operating Licence (TOL) in Malaysia. The Kuantan High Court has adjourned until 10 October 2012 an application by parties associated with the Save Malaysia Stop Lynas (SMSL) group who are seeking an injunction against the TOL.
The deferral of the matter arose from additional affidavits submitted by Lynas. The applicants requested a brief adjournment to respond to those affidavits.”
Lynas waited till the night before the hearing before supplying the affidavits.  It would have known that would cause a deferral.  You may ask why Lynas did that.  I do.
“MALAYSIAN COURT UPDATE 10 October 2012
Lynas Corporation (ASX:LYC, OTC:LYSDY) provides the following update to its ASX announcement dated October 4, 2012. The Kuantan High Court has reserved its decision on an application by parties associated with the Save Malaysia Stop Lynas (SMSL) group who are seeking an injunction against Lynas’ Temporary Operating Licence (TOL).
The injunction relates to an application by SMSL for judicial review of the Minister of Innovation, Science and Technology’s decision in June to dismiss an appeal against the decision of the Atomic Energy Licensing Board (AELB) to award the TOL.
The High Court is scheduled to deliver its decision on 8 November 2012. Until the decision is delivered, the interim order that was issued by the High Court on September 25, 2012 maintaining the status quo in respect of the TOL will remain in place.”
We are now in limbo till the 8th of November when some decision will be handed down by the court.  Perhaps the TOL suspension will be lifted.  Perhaps not.
The situation is abysmal.  Lynas is trading in a vacuum.  Trading needs to be halted until a clear picture of the Company’s future is available.
The Company itself needs to drastically change its attitude to the way it informs the market.  It should give accurate deadlines which are met.  Failure to meet them without sufficient reason should come at a cost to those concerned.
Right now, Nick Curtis bears ultimate responsibility for what has happened.  He needs to be told to change his ways or “it’s the highway”.


Tuesday, 28 August 2012

暂缓莱纳斯临时营运准证 高庭发出两司法审核准令

暂缓莱纳斯临时营运准证
高庭发出两司法审核准令
• Ogos 28, 12 1:57PTG


反莱纳斯稀土厂运动今日迎来一项喜讯,关丹高庭今日批准开审拯救大马委员会的两项申请,
以探讨是否允许司法审核原子能执照局,向莱纳斯发出临时营运准证的决定。

高庭法官玛丽亚娜(Mariana Yahya)今早在内庭聆听总检察署、拯救大马委员会及莱纳斯三方律师陈词后,发出准令,以开审这两项司法审核申请。

挑战莱纳斯营运准证
第一项申请是由拯救大马委员会主席陈文德和两名关丹居民赛卡立(Syed Khalid Syed Sulaiman)与哈希玛(Hasimah Ramli)提出,挑战原子能执照局今年1月批准临时营运准证于稀土厂的决定。

第二项则是由拯救大马委员会副主席依斯迈(Ismail Abu Bakar)和关丹居民陈亚明提出,挑战科学、工艺与革新部长麦西慕今年6月驳回3名关丹居民上诉的决定。

莱纳斯撤销成答辩人
陈文德(左图)告诉《当今大马》,随着法庭批准开审两项申请,政府将不能在司法审核完结前,向莱纳斯发出临时营运准证。

此案答辩人是代表政府的总检察署,而莱纳斯则以这项申请将影响该公司运作为由,申请同列为答辩人。

不过,让陈文德意外的是,莱纳斯律师团今早在内庭中,在毫无预兆下向法官表示撤销申请为答辩人。

他说,由于总检察署也同意进行司法审核,因此法官顺应双方,同意开审拯救大马委员会的两项申请。

他说,法庭与双方律师将会尽快择定开审此案的日期。

“小小民主精神胜利”
陈文德形容,今日的裁决是“小小的民主精神胜利”,彰显我国的民主并未完全灭亡。

“民主精神是三权分立,在民主国家,应该由司法来监督行政偏差,司法必须维护人民的利益。”

原子能执照局是于1月杪同意,批准临时营运准证予莱纳斯稀土厂。不过,准证迄今还未正式发出。

之后,拯救大马委员会副主席依斯迈阿布巴卡(Ismail Abu Bakar)与两名关丹居民陈亚明和阿布加瓦里(Abujavalli V Raman),便针对这项决定,向麦西慕提出上诉。

无论如何,麦西慕驳回上诉,表示该部不会撤回临时营运准证,但会增加两项新的放射性废料处理条件。

‘828’ 司法审核的官司文宣短文

第一篇:一路走来
去年7月24日星期天早晨举办的一场反莱纳斯家庭日,市民为守护美丽的关丹歌颂着。

人类的争端,自古以来都会诉诸武力;而战争即为其中一个解决争端的手段。但随着文明的演进,人类逐渐以法规为准则,化解各个不同的争执与冲突。

虽说我们身处文明的21世纪,可是在面对争纷时,有时也难免会激起人类原始的冲动,不顾法规的存在,一味以自己的意愿去解决纠纷,以致发生不少人为悲剧。

今天,莱纳斯在我们安居已久的美丽家园附近设立稀土厂,难免会引争端,激起公愤。

回顾过去一路走来,人民已经清清楚楚的拒绝了这间提炼厂,然而政府似乎不加理会,相关的部长也充耳不闻,甚至做出了违反情理的决定,让人民心中的刺刺痛紧绷的神经。长此下去, 不知是否有一天,人们还会继续信任法规吗?

“拯救大马委员会”(SMSL)自成立以来,便明确的相信一切的纠纷可以通过正确的管道解决。我们上了我国国会,去了澳洲大使馆,澳洲国会,西澳州议会;我们也见了首相,见了大使;跟澳洲执政和反对党的党魁会面;亦会见了西澳的市长,除了获得礼貌及言语上的支持与承诺之外,一切都回归原状。

虽说如此,我们却上了一堂宝贵的课: 求人还不如求己!

我们通过既有的条款,向有关部长要求撤回AELB的决定,也出席了由部长主持的听证会,提供了不下2000页的科学证据,但这一切却被一句“不具科学与科技”给打发了!


有关部长之前曾在各场所发表偏颇莱纳斯的言论,花费公币刊登全版广告支持AELB的决定,同时印刷小册子,为莱纳斯背书,发表和持有不公和不正的言论和立场,却又当听证会主席,这又怎能说服民众?

职是之故,部长不撤回AELB的决定可以受到法庭的审核。 SMSL将在本月28 日要求法庭审核部长之前做出的决定。


第二篇: 您被说服了吗?
今年的3月17日,拯救大马委员会带领市民拜访怡宝红泥山稀土厂的旧址,获得当地村民的支援。图里的背景就是那至今还未建好的永久埋毒槽!

政府通过国会遴选委员会说,稀土厂很安全,您相信吗?

政府说国际核能调查团的专员,为莱纳斯设下了11 项建议,确保这间稀土提炼厂的操作不至于影响周遭的环境与人们的健康,您们还担心什么?

莱纳斯说固体废料的放射性元素稀少,可以循环作为工业用途,您有听说过吗?

莱纳斯也说它是一间化学工厂,利用高科技生产,不会污染空气和水源,您认为呢?
政党与政客信誓旦旦的说;如果莱纳斯不把产生的有放射性固体废料运出国,他们一定反对到底, 您认为信得过吗?

SMSL和45个民间团体,签署了一封致首相的公开信,揭露了这间厂的某些弊端,结果只有SMSL被告上法庭,要求法庭颁发禁口令,接着还要告SMSL诽谤!

现在您该相信了吧?相信什么?

当TOL被发出去时,莱纳斯曾经提供了固体放射性废料的处理方案,供人们“阅读”。区区300多页充满科学数据的方案,只限阅者一小时阅读。后来虽不设限,却不准公众影印,阅者提供了不下千多份意见,但有关部门却只在区区2个工作日“搞定”所有的意见书。

在处理固体废料方案中,莱纳斯有提及它将把废料转化成可供利用的工业原料。过去4年他们都在研究,可是今天还不见发表任何具体的成果。

莱纳斯稀土厂每年生产4万吨具放射性废料,这些废料不是你我熟悉的100 或1000公斤。如果它真的有了解决方案,它应该已设立了废料循环厂。您有看到或听到设立这样的厂房消息吗?

如果它不能也不打算循环如此庞大的具放射性固体的废料,那它不是要让这批废料永远弃置在我们的国土,让我们的子子孙孙“守护”着它?您认同这样的处置方案吗?

处理方案中也有提及,假设没办法再循环,它将设立永久储藏糟。储藏糟的地点呢?至今它还没开口交代, 您还能相信它的诚意吗?

在这样的情况下,政府是否应该颁发TOL与莱纳斯,让它为我国子民留下“亿万年也腐败不了的工业剧毒废料”?


第三篇:我们是第三世界的蠢民?
这一年来,拯救大马委员会跑偏了半岛以把反稀土的诉求分享出去,也成功联系东马的维权组织。图为于8月4号在吉隆坡召开的第一次全国代表圆桌会议进行后拍的合照。

莱纳斯来我国投资12 亿,建立了世界最大的稀土厂,名为我国提供就业机会,提高经济收入。它一年的营业额高达80亿,相等于我国年经济收益的1%。照理说它应该是会让我国得益不少,可是我国政府却对它偏爱有加,给它12年免课税!这又是什么逻辑?

有人说反莱纳斯的人都被误导了, 真的吗?

回顾去年的八月26日晚间,金满楼酒家挤满了千多个热爱自己家园的市民,为了支持反莱纳斯运动,他们都慷慨的捐献了金钱和出一己的力量,他们是否都被愚弄了?他们都是不懂思考的愚民吗?

SMSL自从去年3月开始推动反莱纳斯稀土厂运动以来,从本地的无数讲座到全国巡回讲座,历经18个月的考验,终于在今年7月14号那天,发动了全国及澳洲同步反莱纳斯公投,获得了3万多人的响应,他们都是被误导了吗?

人们在问,有如此庞大经济效益的工业为什么不留在澳洲,却迢迢千里的把它搬来我国?我们真的那么愚蠢,不知道它来这里的真正原因吗?

有学者说,一些高度发展的第一国家,通常都不让有毒的工业在自己的国度设立。它们会把它输出国外。让他们青睐的国度,都具备一些共同的特点。除了专制,它还是一个充满封建的国度,贪污贿赂横行,人民教育水准不高,普遍失业,监管条例疏松,一切是以人说了算,视法规如无物。

我们是不是一如学者所说的类似的国度?不然莱纳斯又怎会选择了我国成为它设厂的目标?在澳洲人的眼中,我们真的那么愚蠢吗?

我们要不要再继续蠢下去?让我们赖以生存的环境继续受到污染和摧毁?让我们祖先莘勤建立起来的家园,毁于一旦?让我们的子孙,用他们的生命“守护”着任由他人遗留下来的有毒废料?

这个8月28号,拯救大马委员会将通过司法途径,向法庭要求司法审核,坚决反对部长和政府颁发操作执照与莱纳斯!

到时希望不再坐以待毙的关丹市民,踊跃出席当天的审讯。